Project Highlights

Neshaminy 36-inch Transmission Main

Customer: Aqua Pennsylvania

Project Value: $10 MM

Project Highlights:

  • Construction of approximately 20,000 feet of 36-inch TR FLEX Ductile Iron Pipe.
  • Install Meter pit and multiple tie-ins.
  • Close Coordination with PennDot and SEPTA
  • Project completed on time and within budget.
Read More...

Graterford Prison

Customer: PECO Energy

Project Value: $700,000

Project Highlights:
• Construction of more than 7,000 feet of 12-inch steel main on public roadway;
• An additional 2,400 ft of 8-inch steel service on Prison property;

Read More...

Maryland Inter-County Connector

As part of the 1.1M natural gas pipeline relocations in Montgomery County, ULS relocated steel and plastic gas pipelines to ten separate locations. ULS moved 6-20 inch steel pipelines and 4-12 inch plastic pipelines, and installed the steel pipes on bridge overpasses and directional bores of 550 and 530 feet. ULS collaborated professionally with both Intercounty Constructors and MD200 Constructors for phases A and B of this project.

Read More...

Dranesville Gate Station – Dranesville, VA (Washington Gas)

ULS performed all civil, mechanical, instrumentation and electrical work for the installation of a gas conditioning system at Washington Gas Light’s Dranesville Gate Station. ULS installed a 1200ft, 12″ steel transmission main extension.

Read More...

Prince Georges County, Maryland

ULS participated in a three year replacement project in Prince Georges County, MD. ULS replaced more than 24 miles of bare steel main and 6470 steel service lines for Washington Gas Light Co. Working in established neighborhoods, ULS used directional bore methods for the new main installation. Service replacements were done by insertion or direct buried.

Read More...
©2017 Utility Line Services, INC | 1302 Conshohocken Road, Suite 100 | Conshohocken, PA 19428 | 610-239-0900